[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148917,802,1,"单选题","以下脚手架工程专项施工方案必须进行专家论证的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","高度40m及以上落地式钢管脚手架",false,{"key":16,"text":17,"correct":14},"B","提升高度80m及以上附着式整体提升脚手架",{"key":19,"text":20,"correct":14},"C","提升高度60m及以上附着式分片提升脚手架",{"key":22,"text":23,"correct":24},"D","分段架体搭设高度20米及以上的悬挑式脚手架工程",true,"2020教材P319 \u002F 2019教材P321 4）脚手架工程①搭设高度50m及以上落地式钢管脚手架工程。 ②提升高度150m及以上附着式升降脚手架工程或附着式升降操作平台工程。③分段架体搭设高度20米及以上的悬挑式脚手架工程",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]