[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148914,802,1,"单选题","深度为15m的人工挖孔桩工程，（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不需要编制专项方案也不需要专家论证",false,{"key":16,"text":17,"correct":14},"B","不需要编制专项方案但需要专家论证",{"key":19,"text":20,"correct":14},"C","要编制专项方案并需要专家论证",{"key":22,"text":23,"correct":24},"D","要编制专项方案但不需要专家论证",true,"2020教材P319 \u002F 2019教材P320 施工单位应当在危性较大的分部分项工程施工前编制专项方案；对于超过一定规模的危险性较大的分部分项工程，施工单位应当组织专家对专项方案进行论证：开挖深度超过16m的人工挖孔桩工程。本试题是人工挖孔桩是15m，所以只需要编制专项施工方案，不需要专家论证。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]