[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148903,802,1,"单选题","施工成本分析的内容，不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期成本分析",false,{"key":16,"text":17,"correct":18},"B","业务招待分析",true,{"key":20,"text":21,"correct":14},"C","资金成本分析",{"key":23,"text":24,"correct":14},"D","施工索赔分析","2020教材P310 \u002F 2019教材P311 （二）施工成本分析的内容：1.按施工进展进行的成本分析包括：分部分项工程分析、月（季）度成本分析、年度成本分析、竣工成本分析。2.按成本项目进行的成本分析包括：人工费分析、材料费分析、机具使用分析、其他直接费分析、间接成本分析。3.针对特定问题和与成本有关事项的分析：包括：施工索赔分析、成本盈亏异常分析、工期成本分析、资金成本分析、技术组织措施节约效果分析、其他有利因素和不利因素对成本影响的分析。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]