[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148899":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148899,802,1,"单选题","下列文件不属于项目成本控制依据的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程承包合同",false,{"key":16,"text":17,"correct":18},"B","施工设计图纸",true,{"key":20,"text":21,"correct":14},"C","工程进度报告",{"key":23,"text":24,"correct":14},"D","工程变更","2020教材P304 \u002F 2019教材P305 施工成本目标控制主要依据：（一）工程承包合同（二）施工成本计划（三）进度报告（四）工程变更。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]