[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148895,802,1,"单选题","施工成本目标控制主要依据之一的（ ）提供了施工成本实际支付情况，以便通过实际情况与施工成本计划相比较，找出二者之间的差别，分析偏差产生的原因，从而采取措施加以改进。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","成本分析",false,{"key":16,"text":17,"correct":14},"B","成本核算",{"key":19,"text":20,"correct":14},"C","成本计划",{"key":22,"text":23,"correct":24},"D","进度报告",true,"2020教材P304 \u002F 2019教材P305 （三）进度报告 提供了时限内工程实际完成量以及施工成本实际支付情况等重要信息。施工成本控制工作就是通过实际情况与施工成本计划相比较，找出二者之间的差别，分析偏差产生的原因，从而采取措施加以改进。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]