[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148890":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148890,802,1,"单选题","施工项目管理的最终目标是建成质量高、工期短、安全的、成本低的工程产品，所以（ ）是项目管理的核心内容。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量管理",false,{"key":16,"text":17,"correct":14},"B","工期管理",{"key":19,"text":20,"correct":14},"C","安全管理",{"key":22,"text":23,"correct":24},"D","成本管理",true,"2020教材P300 \u002F 2019教材P301 （一）（3）施工项目管理的最终目标是建成质量高、工期短、安全的、成本低的工程产品，而成本是各项目标经济效果的综合反映；因此成本管理是项目管理的核心内容。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]