[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148884":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148884,802,1,"单选题","施工前准备阶段，建设单位延期发出图纸，承包方（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可提出工期和费用索赔",false,{"key":16,"text":17,"correct":18},"B","可提出工期索赔，但不可提出费用索赔",true,{"key":20,"text":21,"correct":14},"C","可提出费用索赔，但不可提出工期索赔",{"key":23,"text":24,"correct":14},"D","不可提出工期和费用索赔","2020教材P296 \u002F 2019教材P297 三、（一）、延期发出图纸产生的索赔接到中标通知书后28d内，承包方有权免费得到由发包方或其委托的设计单位提供的全部图纸、技术规范和其他技术资料，并且向承包方进行技术交底。如果在28d内未收到监理工程师送达的图纸及其相关资料，作为承包方应依据合同提出索赔申请，接中标通知书后第29d为索赔起算日，收到图纸及相关资料的日期为索赔结束日。 由于是施工前准备阶段，该类项目一般只进行工期索赔。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]