[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148883":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148883,802,1,"单选题","当索赔事件持续进行时，承包方应当（ ）向监理工程师发出索赔意向。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","阶段性",true,{"key":16,"text":17,"correct":18},"B","持续",false,{"key":20,"text":21,"correct":18},"C","最终",{"key":23,"text":24,"correct":18},"D","推迟","2020教材P296 \u002F 2019教材P297 （四）持续性索赔事件当索赔事件持续进行时，承包方应当阶段性地向监理工程师发出索赔意向通知，在索赔事件终了后28d内，向监理工程师提出索赔的有关资料和最终索赔报告。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]