[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148879":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148879,802,1,"单选题","施工过程中遇到的合同变更，（ ）必须掌握变更情况，遵照有关规定及时办理变更手续。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":14},"B","业主代表",{"key":19,"text":20,"correct":21},"C","项目负责人",true,{"key":23,"text":24,"correct":14},"D","企业负责人","2020教材P293 \u002F 2019教材P294 三（一）（1）施工过程中遇到的合同变更，如工程量增减，质量及特性变更，工程标高、基线、尺寸等变更，施工顺序变化，永久工程附加工作、设备、材料和服务的变更等，项目负责人必须掌握变更情况，遵照有关规定及时办理变更手续。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]