[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148877":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148877,802,1,"单选题","工程接收证书颁发时，尚有部分未竣工工程的，（ ）应负责该未竣工工程的照管和维护。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包方",false,{"key":16,"text":17,"correct":18},"B","承包方",true,{"key":20,"text":21,"correct":14},"C","分包方",{"key":23,"text":24,"correct":14},"D","承包方、分包方","2020教材P293 \u002F 2019教材P294 （三）（5）工程接收证书颁发前，承包人应负责照管和维护工程。工程接收证书颁发时尚有部分未竣工工程的，承包人还应负责该未竣工工程的照管和维护工作，直至竣工后移交给发包人为止。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]