[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148871,802,1,"单选题","招标工程以（ ）28d为基准日，其后国家的法律、法规、规章和政策发生变化影响工程造价的，应按省级或行业建设主管部门或其授权的工程造价管理机构发布的规定调整合同价款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投标截止日前",true,{"key":16,"text":17,"correct":18},"B","投标截止日后",false,{"key":20,"text":21,"correct":18},"C","中标后",{"key":23,"text":24,"correct":18},"D","合同签订前","2020教材P290 \u002F 2019教材P291 （6）招标工程以投标截止日前28d，非招标工程以合同签订前2 8d为基准日，其后国家的法律、法规、规章和政策发生变化影响工程造价的，应按省级或行业建设主管部门或其授权的工程造价管理机构发布的规定调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]