[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148870":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148870,802,1,"单选题","投标人经复核对招标人公布的招标控制价有异议的，应在招标控制价公布后（ ）d内，向管理机构投诉。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","28","2020教材P290 \u002F 2019教材P291 （5）投标人经复核认为招标人公布的招标控制价未按照工程量清单编制依据的规定编制的，应在招标控制价公布后5d内，向招投标监督机构或（和）工程造价管理机构投诉。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]