[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148869":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148869,802,1,"单选题","施工中出现施工图纸（含设计变更）与工程量清单项目特征描述不符的，发、承包双方应按（ ）确定相应工程量清单的综合单价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","新的项目特征",true,{"key":16,"text":17,"correct":18},"B","类似项目",false,{"key":20,"text":21,"correct":18},"C","合同约定",{"key":23,"text":24,"correct":18},"D","市场价格","2020教材P290 \u002F 2019教材P291 （3）施工中出现施工图纸（含设计变更）与工程量清单项目特征描述不符的，且该变化引起工程造价增减变化的，应按照实际施工的项目特征，以规范相关条款的规定重新确定相应工程量清单项目的综合单价，并调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]