[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148867":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148867,802,1,"单选题","工程计量时，若发现工程量清单中出现漏项或计算偏差，应按承包人在履行合同义务过程中（ ）的工程量计算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","增加",false,{"key":16,"text":17,"correct":14},"B","合同约定",{"key":19,"text":20,"correct":14},"C","减少",{"key":22,"text":23,"correct":24},"D","实际完成",true,"2020教材P290 \u002F 2019教材P291 （2）施工中进行工程计量，当发现招标工程量清单中出现缺项、工程量偏差，或因工程变更引起工程量增减，应按承包人在履行合同义务过程中完成的工程量计算。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]