[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148865":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148865,802,1,"单选题","工程量清单计价模式是指按照国家统一的工程量计算规则，工程数量采用（ ）的形式计算工程造价的方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合单价",true,{"key":16,"text":17,"correct":18},"B","企业定额",false,{"key":20,"text":21,"correct":18},"C","预算定额",{"key":23,"text":24,"correct":18},"D","市场价格","2020教材P289 \u002F 2019教材P290 （2）工程量清单应采用综合单价计价。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]