[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148860,802,1,"单选题","设计概算批准后，一般不得调整。若影响工程概算的主要因素已经清楚，且已通过审批同意，工程量完成了一定量后方可进行调整，但一个工程项目只允许调整（ ）概算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一次",true,{"key":16,"text":17,"correct":18},"B","三次",false,{"key":20,"text":21,"correct":18},"C","两次",{"key":23,"text":24,"correct":18},"D","四次","2020教材P286 \u002F 2019教材P287 （四）（1）设计概算批准后，一般不得调整。由于下列原因需要调整概算时，由建设单位调查分析变更原因，报主管部门审批同意后，由原设计单位核实编制调整概算，并按有关审批程序报批.（2）影响工程概算的主要因素已经清楚，工程量完成了一定量后方可进行调整，一个工程项目只允许调整一次概算。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]