[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148856":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148856,802,1,"单选题","建设项目设计概算是（ ）阶段，由设计单位按设计内容概略算出该工程立项开始到交付使用之间的全过程发生的建设费用文件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可行性研究",false,{"key":16,"text":17,"correct":14},"B","方案设计",{"key":19,"text":20,"correct":21},"C","初步设计",true,{"key":23,"text":24,"correct":14},"D","施工图设计","2020教材P285 \u002F 2019教材P286 工程设计概算是初步设计或扩大初步设计阶段，由设计单位按设计内容概略算出该工程立项从开始到交付使用之间全过程发生的建设费用文件。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]