[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148853,802,1,"单选题","（ ）应按照招标人在招标控制价的其他项目费中相应列出的金额计算，不得修改和调整。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂列金额",true,{"key":16,"text":17,"correct":18},"B","担保金额",false,{"key":20,"text":21,"correct":18},"C","单价金额",{"key":23,"text":24,"correct":18},"D","设备单价","2020教材P284 \u002F 2019教材P285 （5）暂列金额应按照招标人在招标控制价的其他项目费中相应列出的金额计算，不得修改和调整。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]