[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148850,802,1,"单选题","技术标书编制不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","主要施工方案",false,{"key":16,"text":17,"correct":14},"B","安全文明施工措施",{"key":19,"text":20,"correct":21},"C","公司组织机构",true,{"key":23,"text":24,"correct":14},"D","安全管理","2020教材P283 \u002F 2019教材P284 技术部分：（1）主要施工方案2）进度计划及措施（3）质量保证体系及措施（4）安全管理体系及措施（5）消防、保卫、健康体系及措施（6）文明施工、环境保护体系及措施（7）风险管理体系及措施（8）机械设备配备及保障（9）劳动力、材料配置计划及保障（10）项目管理机构及保证体系（11）施工现场总平面图.",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]