[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148842,802,1,"单选题","招标与评标程序中，表述错误的为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","评标专家应在评标专家库采用计算机随机抽取并采取严格的保密措施和回避制度",false,{"key":16,"text":17,"correct":14},"B","对于技术较为复杂工程项目的技术标书，应当暗标制作、暗标评审",{"key":19,"text":20,"correct":21},"C","应采用综合评估的方法，一般情况下技术部分的分值权重可高于商务部分的分值权重",true,{"key":23,"text":24,"correct":14},"D","所有的评标标准的方法必须在招标文件中详细载明，以最大程度地削减评标专家的自由裁量权","2020教材P281 \u002F 2019教材P282 （三）（3）采用综合评估的方法，但不能任意提高技术部分的评分比重，一般技术部分的分值权重不得高于40%，报价和商务部分的分值权重不得少于60%。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]