[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148827,802,1,"单选题","施工测量作业人员应遵循()的原则，掌握工程测量的各种测量方法及相关标准，熟练使用测量器具正确作业，满足工程施工需要。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由整体到局部，先控制后细部",true,{"key":16,"text":17,"correct":18},"B","由局部到整体，先细部后控制",false,{"key":20,"text":21,"correct":18},"C","由设计到实施，先测量后施工",{"key":23,"text":24,"correct":18},"D","由设计到实施，先施工后测量","2020教材P260 \u002F 2019教材P261 施工测量是一项琐碎而细致的工作，作业人员应遵循“由整体到局部，先控制后细部”的原则，",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]