[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148818,802,1,"单选题","聚乙烯（HDP E）膜防渗层施工，采用双缝热熔焊接，焊接前应去除灰尘、（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水分",false,{"key":16,"text":17,"correct":14},"B","裱膜",{"key":19,"text":20,"correct":14},"C","焊条",{"key":22,"text":23,"correct":24},"D","污物",true,"2020教材P251 \u002F 2019教材P252 焊接前应去除灰尘、污物，使搭接部分保持清洁、干燥。焊接部位不得有划伤、污点、 氺分、 灰尘以及其他妨碍焊接和影响施工质量的杂质。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]