[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148807,802,1,"单选题","综合管廊模板施工前，应根据（）、施工工艺、设备和材料供应条件进行模板及支架设计。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","规划",false,{"key":16,"text":17,"correct":14},"B","业主要求",{"key":19,"text":20,"correct":14},"C","合同规定",{"key":22,"text":23,"correct":24},"D","结构形式",true,"2020教材P246 \u002F 2019教材P247 (1)综合管廊模板施工前，应根据结构形式、施工工艺、设备和材料供应条件进行模板及支架设计。模板及支撑的强度、刚度及稳定性应满足受力要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]