[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148799,802,1,"单选题","埋地燃气管道，必须回填土至管顶（ ）以上后才可进行气密性试验。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.2m",false,{"key":16,"text":17,"correct":18},"B","0.5m",true,{"key":20,"text":21,"correct":14},"C","1.0m",{"key":23,"text":24,"correct":14},"D","0.8m","2020教材P243 \u002F 2019教材P244 （2）严密性试验应在强度试验合格且燃气管道全部安装完成后进行。若是埋地敷设，必须回填土至管顶0.5 m以上后才可进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]