[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148753":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148753,802,1,"单选题","热力管网试运行的时间为：应在设计参数下连续热运行（ ）h。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","24",false,{"key":16,"text":17,"correct":14},"B","36",{"key":19,"text":20,"correct":14},"C","48",{"key":22,"text":23,"correct":24},"D","72",true,"2020\u002F2019教材P230 四、试运行工程已经过有关各方预验收合格且热源已具备供热条件后，对热力系统应按建设单位、设计单位认可的参数进行试运行，试运行的时间应为连续运行72h。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]