[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148732,802,1,"单选题","钢管坡口焊接时，焊接层数不得少于（ ）层，每层焊完后，清除熔渣、飞溅物，同一部位焊缝的返修不得超过（ ）次。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2.2",true,{"key":16,"text":17,"correct":18},"B","3.2",false,{"key":20,"text":21,"correct":18},"C","2.3",{"key":23,"text":24,"correct":18},"D","3.3","2020\u002F2019教材P220 （7）电焊连接有坡口的钢管和管件时，焊接层数不得少于两层。每层焊完后，清除熔渣、飞溅物，并进行外观检查，发现缺陷，铲除重焊。不合格的焊接部位，应采取措施返修，同一部位焊缝的返修不得超过两次。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]