[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148711,802,1,"单选题","沟槽开挖规定，槽底原状地基土不得扰动，机械开挖时槽底预留（ ）土层由人工开挖至设计高程，整平。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100～200mm",false,{"key":16,"text":17,"correct":14},"B","50～100mm",{"key":19,"text":20,"correct":21},"C","200～300mm",true,{"key":23,"text":24,"correct":14},"D","100～150mm","2020教材P201 \u002F 2019教材P202 二（一）（1）槽底原状地基土不得扰动，机械开挖时槽底预留200—300mm土层，由人工开挖至设计高程，整平。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]