[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148690,802,1,"单选题","预制曲梁安装时应在梁的跨中临时支撑，待上部二期混凝土达到设计强度的（ ）及以上时，方可拆除支撑。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","70%",false,{"key":16,"text":17,"correct":14},"B","60%",{"key":19,"text":20,"correct":14},"C","50%",{"key":22,"text":23,"correct":24},"D","75%",true,"2020教材P192 \u002F 2019教材P193 预制构件安装就位后，应采取临时固定措施。曲梁应在梁的跨中临时支撑，待上部二期混凝土达到设计强度的75%及以上时，方可拆除支撑。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]