[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148679,802,1,"单选题","给水与污水处理厂试运转联机运行要求，全厂联机运行应不少于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","48h",false,{"key":16,"text":17,"correct":14},"B","12h",{"key":19,"text":20,"correct":21},"C","24h",true,{"key":23,"text":24,"correct":14},"D","5h","2020教材P187 \u002F 2019教材P189 全场联机运行应不少于24h。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]