[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148678,802,1,"单选题","符合给水与污水处理厂连续试运行要求的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","连续试运行期间，开机、停机不少于2次",false,{"key":16,"text":17,"correct":18},"B","水处理和泥处理工艺系统试运行满足工艺要求",true,{"key":20,"text":21,"correct":14},"C","处理设备及泵房单机组累计运行达36h",{"key":23,"text":24,"correct":14},"D","处理设备及泵房机组联合试运行时间，一般不少于3h","2020教材P187 \u002F 2019教材P189 （六）联合试运行：（1）联合试运转应带负荷运行，试运转持续时间不应小于72h，设备应运行正常、性能指标符合设计文件的要求。（2）连续试运行期间，开机、停机不少于3次。（3）处理设备及泵房机组联合试运行时间，一般不少于6h。（4）水处理和泥处理工艺系统试运行满足工艺要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]