[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148645,802,1,"单选题","以下关于隧道工程防水说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工期间的防水措施主要是排、截和堵",false,{"key":16,"text":17,"correct":18},"B","当处于地下潜水位以上的贫水稳定地层，在确保安全的前提下，可限量排水",true,{"key":20,"text":21,"correct":14},"C","含水的松散破碎地层不应采用降低地下水位的排水方案",{"key":23,"text":24,"correct":14},"D","当采用降水方案不能满足要求时，应在开挖的同时进行堵水处理","2020教材P177 \u002F 2019教材P179 二、施工方案选择（1）施工期间的防水措施主要是排和堵两类。施工前，根据资料预计可能出现的地下水情况，估计水量，选择防水方案。施工中要做好出水部位、7JC量等记录，按设计要求施做排水系统，确保防水效果。当结构处于贫水稳定地层，同时位于地下潜水位以上时，在确保安全的条件下，可考虑限排方案。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]