[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148617,802,1,"单选题","全断面法适用于地质条件好的地层，围岩必须有足够的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","强度",false,{"key":16,"text":17,"correct":14},"B","抵抗变形能力",{"key":19,"text":20,"correct":21},"C","自稳能力",true,{"key":23,"text":24,"correct":14},"D","不透水性","2020教材P163 \u002F 2019教材P164 （1）全断面开挖法适用于土质稳定、断面较小的隧道施工，适宜人工开挖或小型机械作业。（3）全断面开挖法的优点是可以减少开挖对围岩的扰动次数，有利于围岩天然承载拱的形成，工序简便；缺点是对地质条件要求严格，围岩必须有足够的自稳能力。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]