[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148613,802,1,"单选题","下列对既有结构物所采取的保护措施，不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调査工程条件",false,{"key":16,"text":17,"correct":14},"B","制定专项施工方案",{"key":19,"text":20,"correct":14},"C","监控量测",{"key":22,"text":23,"correct":24},"D","控制影响区域",true,"2020教材P159 \u002F 2019教材P161 首先，应详细调査工程条件、地质条件、环境条件（即既有结构物现况与安全要求），在调査的基础上进行分析与预测、制定防护措施；其次，制定专项施工方案；最后，施工过程中通过监控量测反馈指导施工而确保既有结构物安全。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]