[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148599,802,1,"单选题","给水排水管道工程和厂站工程施工中，常采用的降低地下水位的降水方法不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","辐射井",false,{"key":16,"text":17,"correct":14},"B","喷射井点",{"key":19,"text":20,"correct":21},"C","坎儿井",true,{"key":23,"text":24,"correct":14},"D","潜埋井","2020教材P117 \u002F 2019教材P118 井点降水方法的选用表1K413021中内容，降水方法包含：集水明排、真空井点，喷射井点，渗井，辐射井，电渗井，潜埋井。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]