[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148588,802,1,"单选题","设置内支撑的基坑围护结构，挡土的应力传递路径是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","围护墙→支撑→围檩",false,{"key":16,"text":17,"correct":14},"B","支撑→围檩→围护墙",{"key":19,"text":20,"correct":21},"C","围护墙→围檩→支撑",true,{"key":23,"text":24,"correct":14},"D","围檩→支撑→围护墙","2020教材P125 \u002F 2019教材P126 在软弱地层的基坑工程中，支撑结构承受围护墙所传递的土压力、水压力。支撑结构挡土的应力传递路径是围护（桩）墙→围檩（冠梁）→支撑；在地质条件较好的有锚固力的地层中，基坑支撑可采用土锚和拉锚等外拉锚形式。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]