[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148572,802,1,"单选题","盖挖顺作法的施工顺序：自地表向下开挖一定深度后先浇筑顶板，在顶板的保护下，自上而下开挖、支撑，达到设计高程后（ ）浇筑结构。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由下向上",true,{"key":16,"text":17,"correct":18},"B","由上向下",false,{"key":20,"text":21,"correct":18},"C","由中间向两端",{"key":23,"text":24,"correct":18},"D","由两端向中间","2020教材P98 \u002F 2019教材P99 盖挖顺作法是在棚盖结构施做后开挖到基坑底，再从下至上施作底板、边墙，最后完成顶板，故称为盖挖顺作法。临时路面一般由型钢纵、横梁和路面板组成，其具体施工流程见1K413011-4。由于主体结构是顺作，施工方便，质量易于保证，故顺作法仍然是盖挖法中的常用方法。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]