[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148560,802,1,"单选题","盖挖逆作法是基坑开挖一段后先浇筑顶板，在顶板的保护下，（ ）的施工方法。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自上而下开挖、支撑，由下向上浇筑结构内衬",false,{"key":16,"text":17,"correct":18},"B","施工过程中不需要临时支撑，借助结构顶板、中板自身的水平刚度和抗压强度实现对基坑围护桩的支护作用",true,{"key":20,"text":21,"correct":14},"C","由一侧向另一侧开挖、支撑和浇筑结构内衬",{"key":23,"text":24,"correct":14},"D","由中间向两侧开挖、支撑和浇筑结构内衬","2020\u002F2019教材P100 施工过程中不需要临时支撑，借助结构顶板、中板自身的水平刚度和抗压强度实现对基坑围护桩的支护作用。正确答案B",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]