[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148558":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148558,802,1,"单选题","箱涵顶进冬期施工时，应确保混凝土()满足规范规定或设计要求。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","砂率",false,{"key":16,"text":17,"correct":18},"B","入模温度",true,{"key":20,"text":21,"correct":14},"C","内外温差",{"key":23,"text":24,"correct":14},"D","坍落度","2020教材P94 \u002F 2019教材P95 三、季节性施工技术措施：（5）冬雨期施工应确保混凝土入模温度满足规范规定或设计要求。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]