[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148551,802,1,"单选题","拱桥施工方法选用应根据拱桥的()、结构形式、现场施工条件、施工水平等因素，并经方案的技术经济比较确定合理的施工方法。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","长度",false,{"key":16,"text":17,"correct":14},"B","高度",{"key":19,"text":20,"correct":21},"C","跨度",true,{"key":23,"text":24,"correct":14},"D","宽度","2020教材P86 \u002F 2019教材P87 二）（2）选用施工方法应根据拱桥的跨度、结构形式、现场施工条件、施工水平等因素，并经方案的技术经济比较确定合理的施工方法。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]