[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148547,802,1,"单选题","钢—混凝土组合梁施工中，应随时监测主梁和施工支架的()，确认符合设计要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","高程",false,{"key":16,"text":17,"correct":14},"B","内力",{"key":19,"text":20,"correct":21},"C","变形及稳定",true,{"key":23,"text":24,"correct":14},"D","位移","2020教材P84 \u002F 2019教材P85 7）施工中，应随时监测主梁和施工支架的变形及稳定，确认符合设计要求；当发现异常应立即停止施工并启动应急预案。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]