[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148544":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148544,802,1,"单选题","下面关于在拱架上浇筑砼拱圈表述不正确的是()",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","跨径小于18m的拱圈或拱肋混凝土，应按拱圈全宽从拱圈从两端拱脚向拱顶对称、连续浇筑，并在拱脚混凝土初凝前完成。",true,{"key":16,"text":17,"correct":18},"B","不能完成时，则应在拱脚预留一个隔缝，最后浇筑隔缝混凝土",false,{"key":20,"text":21,"correct":18},"C","跨径大于等于16m的拱圈或拱肋，宜分段浇筑。",{"key":23,"text":24,"correct":18},"D","拱圈封拱合龙时混凝土强度，设计无要求时，各段混凝土强度应达到设计强度的75%","2020\u002F2019教材P88 在拱架上浇筑混凝土拱圈：（1）.跨径小于16m的拱圈或拱肋混凝土，按拱圈全宽度从两端拱脚向拱顶对称连续浇筑，并在拱脚混凝土初凝前全部完成。不能完成时，则在拱脚预留一个隔缝，最后浇筑隔缝混凝土。（2）.跨度大于或等于16m的拱圈或拱肋，应沿拱跨方向分段浇筑。（7）.拱圈（拱肋）封拱合龙时混凝土强度应符合设计要求，设计无要求时，各段混凝土强度应达到设计强度的75%。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]