[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148530":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148530,802,1,"单选题","桥梁墩台预制柱安装后应及时浇筑杯口混凝土，待混凝土硬化后拆除硬楔，浇筑二次混凝土，待杯口混凝土达到设计强度的()后方可拆除斜撑。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","45%",false,{"key":16,"text":17,"correct":14},"B","55%",{"key":19,"text":20,"correct":14},"C","65%",{"key":22,"text":23,"correct":24},"D","75%",true,"2020\u002F2019教材P75 二、预制混凝土柱和盖梁安装：（3）安装后应及时浇筑杯口混凝土，待混凝土硬化后拆除硬楔，浇筑二次混凝土，待杯口混凝土达到设计强度75%后方可拆除斜撑。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]