[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148529,802,1,"单选题","预制钢筋混凝土盖梁安装时，接头混凝土达到()后，方可卸除临时固定设施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计强度",true,{"key":16,"text":17,"correct":18},"B","设计强度90%",false,{"key":20,"text":21,"correct":18},"C","设计强度80%",{"key":23,"text":24,"correct":18},"D","设计强度75%","2020\u002F2019教材P75 二）（3）盖梁就位时，应检査轴线和各部尺寸，确认合格后方可固定，并浇筑接头混凝土。接头混凝土达到设计强度后，方可卸除临时固定设施。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]