[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148522":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148522,802,1,"单选题","灌注水下混凝土时，灌注的桩顶标高应高出设计标高()m，多余部分在接桩前凿除。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5～0.7",false,{"key":16,"text":17,"correct":18},"B","0.5～1.0",true,{"key":20,"text":21,"correct":14},"C","0.7～1.0",{"key":23,"text":24,"correct":14},"D","1.0～1.5","2020\u002F2019教材P73 （6）桩顶混凝土浇筑完成后应高出设计标高0.5～1.0m，确保桩头浮浆层凿除后桩基面混凝土达到设计强度。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]