[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148517":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1148517,802,1,"单选题","正、反循环钻孔达到设计深度，在灌注混凝土之前，孔底沉渣厚度应符合设计要求，设计未要求时摩擦桩的沉渣厚度不应大于()mm。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","200",{"key":19,"text":20,"correct":21},"C","300",true,{"key":23,"text":24,"correct":14},"D","400","2020\u002F2019教材P71 2.（3）钻孔达到设计深度，灌注混凝土之前，孔底沉渣厚度应符合设计要求。设计未要求时端承型桩的沉渣厚度不应大于100mm；摩擦型桩的沉渣厚度不应大于300mm。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]