[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148513":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1148513,802,1,"单选题","围堰的施工顺序为()合龙。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","左岸至右岸",false,{"key":16,"text":17,"correct":14},"B","下游开始至上游",{"key":19,"text":20,"correct":14},"C","右岸至左岸",{"key":22,"text":23,"correct":24},"D","上游开始至下游",true,"2020\u002F2019教材P68 五、（5）围堰施工顺序一般从上游向下游合龙。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]