[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148502,802,1,"单选题","下列关于后张法预应力张拉要求的选项中，说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当同一截面中有多束一端张拉的预应力筋时，张拉端宜均匀交错地设置在结构两端",false,{"key":16,"text":17,"correct":18},"B","张拉前应根据设计要求对孔道的摩阻损失进行实测，以便确定张拉控制应力值和实际伸长值",true,{"key":20,"text":21,"correct":14},"C","预应力筋的张拉顺序当设计无要求时，可采取分批、分阶段对称张拉",{"key":23,"text":24,"correct":14},"D","张拉过程中预应力筋断丝、滑丝、断筋的数量不得超过规定","2020\u002F2019教材P56 张拉前应根据设计要求对孔道的摩阻损失进行实测，以便确定张拉控制应力值，并确定预应力筋的理论伸长值。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]