[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148501":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148501,802,1,"单选题","钢绞线束或钢丝束施工时，下列选项中，适用于没有自锚性能锚具的后张法预应力筋张拉程序有()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0→初应力→1.03σcon（锚固）",false,{"key":16,"text":17,"correct":18},"B","0→初应力→1.05σcon(持荷2min)→σcon（锚固）",true,{"key":20,"text":21,"correct":14},"C","0→初应力→σcon（持荷2min锚固）",{"key":23,"text":24,"correct":14},"D","低松弛力筋0→初应力→σcon（持荷2min锚固）","2020\u002F2019教材P56 表1K412015-3。其它锚具是：0→初应力→1.05σcon(持荷2min)→σcon（锚固）",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]