[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1148487,802,1,"单选题","市政公用工程中，混凝土配合比设计要经过四个步骤，其中在施工配合比设计阶段进行配合比调整并提出施工配合比的依据是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实测砂石含水率",true,{"key":16,"text":17,"correct":18},"B","配制强度和设计强度间关系",false,{"key":20,"text":21,"correct":18},"C","施工条件差异和变化及材料质量的可能波动",{"key":23,"text":24,"correct":18},"D","强度验证原理和密度修正方法","2020\u002F2019教材P50 三、混凝土配合比设计步骤：（4）施工配合比设计阶段，根据实测砂石含水率进行配合比调整，提出施工配合比。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]