[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1148473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1148473,802,1,"单选题","混凝土桩制作时，预制构件的吊环必须采用()制作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","经过冷拉的HPB300级热轧钢筋",false,{"key":16,"text":17,"correct":18},"B","未经过冷拉的HPB300级热轧钢筋",true,{"key":20,"text":21,"correct":14},"C","HRB335级热轧钢筋",{"key":23,"text":24,"correct":14},"D","HRB400级热轧钢筋","2020\u002F2019教材P47 （5）预制构件的吊环必须采用未经冷拉的热轧光圆钢筋制作，不得以其他钢筋替代，且其使用时的计算拉应力应不大于50Mpa。",{"id":6,"name":27,"category":28,"favorite":29},"一建市政公用工程实务","建筑工程",0]